The Concession Agreement means an agreement entered into between a Procuring Entity and a private sector participant for and in respect of a Public-Private Partnership The draft Concession Agreement which shall govern the contractual relations between the Concessionaire and the Procuring Entity detailing the rights and obligations of both the parties, definition of the subject matter of the agreement, payment terms, performance obligations, defaults and their consequences, events of termination and other ancillary clauses as provided in Schedule-I of this rule.
1. Provisions of the DCA:
The link for online submission of Draft Concession Agreement is - https://tnidb.tn.gov.in/en/documents/bid-documents/
TNID Act 2012 | |
---|---|
Section 17 |
(c) ·the appropriate concession agreement or a combination thereof, from out of those listed in Schedule II. |
Section 18(4) |
(4) The procuring entity shall, in respect of Projects identified by the Board, intimate the name and address of the tenderer whose tender has been accepted, to the Board and shall also obtain its approval on the concession agreement to be entered into with such tenderer. |
TNID Regulations 2013 | |
---|---|
Regulation 15 |
Approval of Tender Documents and Concession Agreement(1) The Board may prescribe standard tender documents for adoption for different types of projects and such standard documents may be used for procurement wherever available. (2) Until such standard tender documents are prescribed, the public agency or sponsoring agency, as the case may be, shall submit the draft tender documents for the prior approval of the Board. (3) In the case of Public Private Partnership projects, the sponsoring agency may where applicable follow the model tender documents and model concession agreements for Public Private Partnership projects prepared by the Union Planning Commission as the base, with such modifications as may be necessary. (4) All tender documents including draft concession agreements for Public Private Partnership projects shall require the prior approval of the Board and any substantive changes made during pre-tender consultations with prospective tenderers shall also be approved by the Board. (5) The sponsoring agency may with the prior concurrence of the Board issue a Request for Expression of Interest at any time and even the project scope and structure are finalized by the Board under section 17 of the Act. (6) The sponsoring agency shall issue the Request for Quotations only after the project scope and structure have been finalized by the Board under section 17 of the Act and the financial support from Tamil Nadu Infrastructure Development Fund, if any, is approved under rule 12 of the Tamil Nadu Infrastructure Development Rules. (7) The sponsoring agency shall forward to the Board, the Concession Agreement to be signed with the tenderer whose tender has been accepted with a certificate that no changes have been affected in the final Draft Concession Agreement which formed part of the Request for Proposal (RFP). |
TNTIT(PPP) Rules, 2012 | |
---|---|
Rule 59 |
Tender Finalization and Award.(1) The results of evaluation of tenders shall be submitted to the Tender Accepting Authority for approval. (2) The Lowest Tenderer shall be notified by the Tender Inviting Authority after obtaining approval of the Tender Accepting Authority. (3) On receipt of approval of the Tender Accepting Authority, the Tender Inviting Authority shall communicate to other Tenderers about the selection of the Lowest Tenderer, and its intention to execute the Concession Agreement with the Lowest Tenderer. (4) After selection, a Letter of Award (LOA) shall be issued, in duplicate, by the Procuring Entity to the Lowest Tenderer with the condition that the Lowest Tenderer shall, within 7 (seven) days of the receipt of the Letter of Award (LOA), sign and return a duplicate copy of the Letter of Award (LOA) in acknowledgement thereof. (5) Subject to fulfilment of the requirements specified in the Request for Proposal (RFP) and of the Letter of Award (LOA) the Lowest Tenderer will be required to enter into a Concession Agreement with the Procuring Entity and the Procuring Entity shall execute the Concession Agreement with the Lowest Tenderer. |
Rule 60 |
Monitoring of Concession Agreement.(1) Procuring Entity that enters into a Concession Agreement shall make adequate institutional arrangements to monitor the performance of the Concessionaire under such agreement. (2) Such arrangements shall include the receipt, study and corrective action based on the reports of the Independent Engineer and Independent Auditor. |